Overview
Nonhyun Center
Seocho 1 Center
Seocho 2 Center
Daegu Center
  HOME > KIDC Facilities > Seocho 2 Center
 
Center
Click on the images below to view the center map and detailed information of a KIDC center.
Seocho 2 Center
Fire protecion systems Environmentally friendly FM-200 gas suppression System

Early fire detection with smoke and heat detectors cross-wired

Fire zone(CO©ü& FM-200 & Pre-action sprinker)

Fireproof wall and floor
Electric supplying systems Dual grids power feeds from KEPCO

High efficiency Transformer with enough capacity for dual backup

Reliable gas turbine with fuel more than 24 hour running capacity

Parallel static UPS operation with SBM System

Battery Back-Up Time : 1hr
Mechanical
systems
Optimal temperature at 20~23¡É (68.0~73.4¢µ) & humidity of
  40-50%

Down-flow type CRAC for cooling of server rooms

Dual cooling water riser for redundancy

Reliable inverter control of cooling warter pumps with reserved units

N+1 isolated configuration of cooling towers ans pumps

Water detection system, water dam around pipe and drain holes
Security service
& systems
Adva Ntage System & Card Key

Alarm monitoring & System Administration
  (Access Level control, event printout, alarming, log file)

Full interior and exterior security surveillance, monitoring and
  recording of activities

3 shifts of on-site security personnel are on duty 24/7/365